Posts

2024/2/6 4621.03 Polk Co Bridge

Image
Contractor set forms ready to pour concrete tomorrow 

2024/2/5 4621.03 Polk Co Bridge

Image
Tying rebar for bents 1-2

2024/2/2 4621.03 Polk Co Bridge

Image
Finish preboring at bent 2. Start setting pile driver up and prepping to drive pile at bent 2. Set crane up to start pile driving at bent 1 Drive pile at bent 1 Start driving pile at bent 2

2024/2/1 4621.03 Polk Co Bridge

Image
Finish last hole for bent 1 Move over to bent 2 Contractor excavating at bent 1 grading to set up pile driving

2024/1/31 4621.03 Polk Co Bridge

Image
Continue to prebore at bent 1 Machine broke down  Repaired machine and started to prebore again

2024/1/30 4621.03 Polk Co Bridge

Image
Preboring at bent 1